F10 Notification

Notify HSE before construction begins on notifiable projects. Required under CDM 2015, Regulation 6.

When is F10 required?

You must notify HSE before the construction phase begins if the project will last longer than 30 working days AND have more than 20 workers on site at any one time, OR exceed 500 person-days of construction work. The notification must be submitted to HSE before construction work starts.

Submit to HSE online at hse.gov.uk/forms/notification/f10.htm or use this tool to generate a pre-filled PDF you can print and submit.

Is your project notifiable?

1. The Project
2. The Client
3. Principal Designer
4. Principal Contractor
5. Dates & Numbers
6. Existing Use & Additional Info
7. Declaration