Notify HSE before construction begins on notifiable projects. Required under CDM 2015, Regulation 6.
You must notify HSE before the construction phase begins if the project will last longer than 30 working days AND have more than 20 workers on site at any one time, OR exceed 500 person-days of construction work. The notification must be submitted to HSE before construction work starts.